Cheltenham General Hospital, General Theatres One and Two

Cheltenham General Hospital, General Theatres One and Two

Client

Gloucestershire Hospitals NHS Foundation Trust

Quattro designed the scheme from inception to completion refurbishing the theatres at the same time with minimal disruption.

No results found.

Quattro led the design team in designing a plug-in site facility with the M&E consultants to service the modular building.

The Challenge

Quattro Design Architects has been the hospital architect of choice for many years designing and delivering major refurbishments of operating theatres as part of a rolling programme for Cheltenham General Hospital.

More recently, Quattro was appointed to design the refurbishment of GT1 and GT2 theatres as well as the reconfiguration spaces to enhance efficiency, preparation and the installation of up-to-date equipment and services for Cheltenham General Hospital.

Quattro designed the scheme from inception to completion refurbishing the theatres at the same time with minimal disruption.

Our Solution

Before works began, the Trust decided that two theatres could not be out of action at the same time, therefore, a modular theatre was implemented as a temporary facility.

Quattro led the design team in designing a plug-in site facility with the M&E consultants to service the modular building. All preparatory works including foundations and services were fully detailed, designed and installed prior to the unit’s delivery.

The unit was delivered on a weekend with no disruption to the hospital and following theatre validation; the unit continues to run successfully.

Project Gallery

Related Projects

Do you have a project in mind?

Quattro Design Architects with over 36 years experience

Do you have an idea for a project you require help with? Contact us today to find out how our dedicated team can help.